Friday 23 May 2014

Lock Up Stage / Fixing Stage complete / Last Final Stage under way

Lock Up Stage Complete 18th April:

- Bricks were completed






Fixing Stage Completed May 2nd:

- Plaster, Architraves, Cornices and Skirtings complete
- Kitchen and Bathroom cupboards complete



Final Stage under way:

- Fit Off's (lights, ducts, power points, switches etc.), Painting completed 16th May
- Bathroom and Kitchen splash-back tiles completed 23 May