- Bricks were completed
Fixing Stage Completed May 2nd:
- Plaster, Architraves, Cornices and Skirtings complete
- Kitchen and Bathroom cupboards complete
Final Stage under way:
- Fit Off's (lights, ducts, power points, switches etc.), Painting completed 16th May
- Bathroom and Kitchen splash-back tiles completed 23 May